Project Overview
Date :
February, 2026
Client :
Ascent Group
Category :
Housing
Location :
Oldham
Pump Station Upgrade & Commissioning Project
We recently completed a full pump station upgrade and commissioning for a client, delivering a complete system overhaul designed to improve reliability, safety, and long-term performance. The project involved replacing critical components, upgrading controls, and carrying out full testing to ensure the station was left fully operational and set to automatic duty.
- Full System Upgrade
- New Control Panel Installed
- Pump & Guide Rail Replacement
- Pipework & Valve Renewal
- Float & Control Verification
- Fully Commissioned & Tested
The Brief
The client required a complete pump station upgrade to address ageing equipment and ensure improved operational reliability. The scope of works focused on replacing key mechanical and electrical components, upgrading control systems, and improving overall system performance. The objective was to leave the pump station fully tested, commissioned, and operating safely in automatic duty.
What We Did
- Control Panel Installation: Installed a brand-new control panel to modernise the system and improve operational control.
- New Pump Supplied & Installed: Supplied and fitted a new pump to enhance reliability and performance.
- Guide Rails & Mounting System: Installed new guide rails and mounting bracket system to improve stability and maintenance access.
- Float Switch Upgrade: Fitted new float switches with bracket assembly to ensure accurate level control and system response.
- Lifting Chain & Shackle Replacement: Installed a new lifting chain and shackle for safer ongoing maintenance access.
- Pipework & Valve Replacement: Replaced pipework including non-return valve, gate valve, and associated fittings to improve system integrity and prevent backflow issues.
Testing & Commissioning
Following installation, full testing and commissioning were carried out.
The system was:
Performance tested
Controls verified
Float operation confirmed
Pump set to automatic duty
The station was left fully operational and ready for service.
Summary
This pump station upgrade delivers improved reliability, safer maintenance access, and long-term operational performance for the client. By replacing ageing components and upgrading controls, the system is now positioned to operate efficiently and reduce the risk of future failures. If you’re experiencing recurring pump failures, control issues, or ageing equipment, we can provide full refurbishment or complete replacement solutions tailored to your site requirements.